Ohio Court of Claims Decision Puts Public Works Bond Sureties Directly Behind the Eight Ball

Body

From the Law Office of Hahn Loeser & Parks LLP.

In Berkley Ins. Co. v. Kent State Univ., Ohio Ct. of Cl. No. 2018-00579JD (Jan. 14, 2019), the Ohio Court of Claims expanded its prior rulings strictly enforcing contract dispute resolution provisions in the public construction contract arena. The Court ruled, despite the circumstances that actually existed between the contracting parties, that a contractor’s surety who takes over and completes a project after the contractor’s default and termination is likewise bound by the contract’s dispute provisions. The ruling reinforces the significant risk of waiver of claims by contractors and their sureties when claims are not promptly submitted in accordance with contract provisions governing disputes, even though all parties are aware of the dispute and claim."